Project:
Project: Commercial Mall grid-tie solar PV project
Project Scope:
As an EPCM contractor, ZPE executed the engineering, procurement, and construction management for this project. This included the design, engineering, and technical project management on behalf of our project partner.
- Installer: Solana Energy
- Installation Date: 22/01/2024
- Location: Western Cape
- 500 kW grid-tie Huawei inverter capacity
- 626 kWp solar capacity
- AC and DC electrical and earthing works
- System has remote monitoring functionality
- Comprehensive electrical and structural engineering design
- Adherence to OH&S act safety and health and environmental compliance
Location: Western Cape, South Africa
Completion Date: March 2024
Client Benefits:
Up to R140 000 monthly bill saving on Eskom electricity bill due to solar power feeding all operational electricity needs during sunlight hours
Potential to feed back excess solar to the utility (current application in progress)