80kWp Rooftop Solar PV + 184kWhr Containerised Li-On Battery School System – Bochum, Limpopo

Covid 19 apr20 IG
ZPE Editorial Team
ZPE Editorial Team
Project: 80kWp Rooftop Solar PV + 184kWhr Containerised Li-On Battery School System – Bochum, Limpopo
Project Scope:

Phase 1: Design & executed a grid-tied solar PV system for a public-sector complex in Limpopo. System includes grid limiting and active control of a grid-tied inverter to allow off-grid functionality of solar PV.

Phase 2: Design and execution of a grid-interactive lithium-ion battery storage system to store excess solar PV in the day and utilise at night and during load shedding to allow the facility to become effectively off-grid.

System includes remote monitoring and control to allow active monitoring and tweaking of system for maximum customisation and optimisation.

Technology:

  • 1x 60kW + 1x 20kW grid-tied solar PV inverters
  •  240x 340Wp Tier 1 solar panels
  • 144kW battery inverter/chargers
  • 36x 5kWhr Li-On batteries
Location: Bochum, Limpopo
Completion Date: Aug 2020